🔧 Engineering & Regulatory Standard

DNO G99 & G100 Grid Connection Guide for Commercial Solar

Navigating DNO Applications, Network Constraints, and Export Limitation Devices

A technical guide explaining Engineering Recommendations G99 and G100, Distribution Network Operator (DNO) application processes, grid connection costs, and export curtailment solutions for commercial solar arrays.

Key Technical Principles

  • Systems exceeding 3.68kW per phase (11.04kW 3-phase) require formal DNO approval under Engineering Recommendation G99 prior to installation
  • DNO application review periods standardly take 45 to 65 working days across the 6 UK regional network operators
  • Engineering Recommendation G100 export limitation systems prevent expensive network reinforcement quotes by capping grid export
  • Meter Point Administration Number (MPAN) and Maximum Import Capacity (MIC) data are critical for initial connection feasibility
  • G99 witness testing is mandatory for larger installations before final energisation and commercial operation
Commercial Feasibility Portal

Request Engineering Desk Feasibility & DNO Assessment

Indicative kWp sizing, G99 grid headroom check & 100% AIA tax shelter calculation.

Stage 1 of 520% Complete

Enterprise Compliance

Vetted UK Commercial EPC Installation Network

Our commercial installation partners are rigorously vetted and accredited to the UK's highest technical, electrical, and site-safety standards:

CHAS Elite

SSIP Acclaimed

SafeContractor

SSIP Member

NICEIC Approved

Commercial Contractor

ISO 9001 / 14001

Quality & Environment

Solar Energy UK

Corporate Member

MCS Certified

Microgeneration Standards

Engineering Recommendation G99 / G100

Commercial Grid Connection Lifecycle

All systems exceeding 11.04kW on a three-phase commercial supply require formal DNO approval before energisation. Here is how our engineering partners navigate the process:

1 Desktop Review

Stage 1: Weeks 1–2

MPAN & Network Desk Study

Review 12 months half-hourly (.csv) import data, Maximum Import Capacity (MIC), and regional DNO substation capacity headroom.

2 Formal Filing

Stage 2: Week 3

Formal G99 Standard Submission

Submit detailed Single-Line Diagram (SLD), inverter type-test certificates, and protection relay settings to the regional DNO.

3 DNO Review

Stage 3: Weeks 4–12

DNO Engineering Network Assessment

Statutory 45 to 65 working day evaluation. Network modeling determines local thermal limits and fault level contributions.

4 Cost Bypass

Stage 4: Engineering Solution

G100 Export Limitation Configuration

If network reinforcement is quoted (>£50k), fail-safe G100 export limiters throttle export to allowable capacity within 5 seconds, bypassing grid charges.

5 Live Energisation

Stage 5: Final energisation

Commissioning & DNO Witness Testing

On-site protection relay witness testing with DNO engineer present, followed by formal issue of the G99 connection compliance certificate.

Covers all 6 GB DNOs: National Grid, UKPN, SPEN, SSEN, Electricity North West, and Northern Powergrid.
Read Complete G99/G100 Guide →

Understanding ENA Engineering Recommendation G99

The Energy Networks Association (ENA) sets the connection criteria for distributed generation. While domestic arrays under 16A per phase connect under simplified G98 notify-and-fit rules, commercial solar installations (>11.04kW on three-phase) fall under Engineering Recommendation G99. This requires a formal technical application submitted to your regional Distribution Network Operator (DNO) before any hardware is energized.

The 6 UK Regional DNOs and Network Realities

Distribution infrastructure in Great Britain is managed by six regional DNOs across 14 licence areas: National Grid Electricity Distribution (Midlands, South West, South Wales), UK Power Networks (London, South East, East), SP Energy Networks (Central & Southern Scotland, North Wales, Merseyside), Scottish and Southern Electricity Networks (North Scotland, Central Southern England), Electricity North West, and Northern Powergrid (North East, Yorkshire). In constrained network areas, DNOs may initially quote significant reinforcement fees for unlimited export.

How G100 Export Limitation Bypasses Substation Upgrade Costs

When a DNO indicates that the local high-voltage or low-voltage network cannot absorb your system's peak generation, installers specify an ENA-approved G100 export limitation device. G100 systems continuously measure power flow at the grid boundary point. If on-site consumption drops below solar output, the G100 controller instantaneously throttles inverter generation within 5 seconds, ensuring export never exceeds the pre-agreed DNO threshold. This allows businesses to install 500kWp+ systems behind the meter without paying £50k–£250k+ in utility network reinforcement charges.

The G99 Application Process & Timeline

1. **Preliminary Network Study & MPAN Review (Week 1–2)**: Review half-hourly import/export data, Maximum Import Capacity (MIC), and local DNO substation headroom capacity. 2. **Formal G99 Standard Application Submission (Week 3)**: Detailed single-line diagram (SLD), protection settings, inverter type-test certificates, and G100 schematic submitted to the DNO. 3. **DNO Assessment Window (Weeks 4–12)**: Statutory 45 to 65 working day evaluation period where DNO electrical engineers model fault level contribution and thermal capacity. 4. **Connection Offer Acceptance**: Review connection terms and export capacity allocation. 5. **Commissioning & DNO Witness Testing**: Certified commissioning and protection relay witness testing prior to permanent commercial operation.

Technical Compliance

Frequently Asked Questions

Facilities managers and engineering team queries

What is the difference between G98, G99, and G100?

G98 applies to micro-generation (up to 16A/phase) and operates on a "fit and notify" basis. G99 governs systems above 16A/phase and requires prior formal DNO consent. G100 specifies technical requirements for fail-safe export limitation schemes that restrict power sent to the grid.

How much does a commercial G99 grid application cost?

DNO engineering assessment fees generally range from £800 to £3,500 depending on installed capacity, connection voltage level (LV vs HV), and whether complex network studies are triggered.

Can a commercial solar project proceed if the DNO grants zero export capacity?

Yes. By installing a G100-compliant export limiter, a business can install an extensive solar array dedicated 100% to on-site self-consumption with zero power exported onto the public grid.