DNO G99 & G100 Grid Connection Guide for Commercial Solar
Navigating DNO Applications, Network Constraints, and Export Limitation Devices
A technical guide explaining Engineering Recommendations G99 and G100, Distribution Network Operator (DNO) application processes, grid connection costs, and export curtailment solutions for commercial solar arrays.
Key Technical Principles
- ✓ Systems exceeding 3.68kW per phase (11.04kW 3-phase) require formal DNO approval under Engineering Recommendation G99 prior to installation
- ✓ DNO application review periods standardly take 45 to 65 working days across the 6 UK regional network operators
- ✓ Engineering Recommendation G100 export limitation systems prevent expensive network reinforcement quotes by capping grid export
- ✓ Meter Point Administration Number (MPAN) and Maximum Import Capacity (MIC) data are critical for initial connection feasibility
- ✓ G99 witness testing is mandatory for larger installations before final energisation and commercial operation
Request Engineering Desk Feasibility & DNO Assessment
Indicative kWp sizing, G99 grid headroom check & 100% AIA tax shelter calculation.
Enterprise Compliance
Vetted UK Commercial EPC Installation Network
Our commercial installation partners are rigorously vetted and accredited to the UK's highest technical, electrical, and site-safety standards:
CHAS Elite
SSIP Acclaimed
SafeContractor
SSIP Member
NICEIC Approved
Commercial Contractor
ISO 9001 / 14001
Quality & Environment
Solar Energy UK
Corporate Member
MCS Certified
Microgeneration Standards
Commercial Grid Connection Lifecycle
All systems exceeding 11.04kW on a three-phase commercial supply require formal DNO approval before energisation. Here is how our engineering partners navigate the process:
Stage 1: Weeks 1–2
MPAN & Network Desk Study
Review 12 months half-hourly (.csv) import data, Maximum Import Capacity (MIC), and regional DNO substation capacity headroom.
Stage 2: Week 3
Formal G99 Standard Submission
Submit detailed Single-Line Diagram (SLD), inverter type-test certificates, and protection relay settings to the regional DNO.
Stage 3: Weeks 4–12
DNO Engineering Network Assessment
Statutory 45 to 65 working day evaluation. Network modeling determines local thermal limits and fault level contributions.
Stage 4: Engineering Solution
G100 Export Limitation Configuration
If network reinforcement is quoted (>£50k), fail-safe G100 export limiters throttle export to allowable capacity within 5 seconds, bypassing grid charges.
Stage 5: Final energisation
Commissioning & DNO Witness Testing
On-site protection relay witness testing with DNO engineer present, followed by formal issue of the G99 connection compliance certificate.
Understanding ENA Engineering Recommendation G99
The 6 UK Regional DNOs and Network Realities
How G100 Export Limitation Bypasses Substation Upgrade Costs
The G99 Application Process & Timeline
Technical Compliance
Frequently Asked Questions
Facilities managers and engineering team queries
What is the difference between G98, G99, and G100?
G98 applies to micro-generation (up to 16A/phase) and operates on a "fit and notify" basis. G99 governs systems above 16A/phase and requires prior formal DNO consent. G100 specifies technical requirements for fail-safe export limitation schemes that restrict power sent to the grid.
How much does a commercial G99 grid application cost?
DNO engineering assessment fees generally range from £800 to £3,500 depending on installed capacity, connection voltage level (LV vs HV), and whether complex network studies are triggered.
Can a commercial solar project proceed if the DNO grants zero export capacity?
Yes. By installing a G100-compliant export limiter, a business can install an extensive solar array dedicated 100% to on-site self-consumption with zero power exported onto the public grid.
Verify Your Facility's Grid & Compliance Status
Our accredited engineering partners perform an initial MPAN desk study to confirm DNO substation capacity and assess RC62 insurance compliance for your building.