An export limit does not replace a generation connection approval.
Plan a commercial solar G99 application and G100 export limitation: inverter capacity, battery topology, DNO offer, commissioning and Northern Ireland differences.
Check grid-connection feasibility for your site
Share your commercial site and energy requirements with Butterfly Eco for review and follow-up.
Enterprise Compliance
Our commercial installation partners are rigorously vetted and accredited to the UK's highest technical, electrical, and site-safety standards:
CHAS Elite
SSIP Acclaimed
SafeContractor
SSIP Member
NICEIC Approved
Commercial Contractor
ISO 9001 / 14001
Quality & Environment
Solar Energy UK
Corporate Member
MCS Certified
Microgeneration Standards
Vetted Commercial Partner
Commercial solar PV, LED lighting and EV charging specialists. Zero-capital Solar as a Service, direct Capex, and sector-specific delivery for businesses, schools and care homes.
View partner profile & processG100 export limitation is not a substitute for G99 approval. Programme and costs depend on the site and network operator; Northern Ireland uses separate NIE Networks routes.
List PV and battery inverter AC capacities, phase arrangement, existing generation and half-hourly site demand.
Confirm G98 or G99 with the network operator; assess a G100 export limit if the proposed export is constrained.
Provide the single-line diagram, equipment and protection details. Allow for questions and a site-specific network assessment.
Check agreed export, any reinforcement, curtailment, charges and conditions before committing to the final design.
Commission protection and any export limiter; complete required witness testing and retain the network approval and as-built settings.
Your installer should list each existing and proposed PV inverter, battery inverter and other generator, with its continuous AC capacity and phase arrangement. Panel kWp is a DC generation rating and is not a substitute for the AC information in a grid application. A battery sharing a DC-coupled hybrid inverter can differ from a battery with its own AC inverter: the latter may add to aggregate inverter capacity and alter the application route. Ask for a single-line diagram showing the connection point and metering.
In Great Britain, eligible microgeneration up to 16 A per phase may use G98, subject to the route’s conditions; do not assume every small or multi-unit proposal is fit-and-notify. Larger schemes generally require a G99 application and network approval before installation. G100 governs an agreed export-limitation scheme, not permission to connect the generator. A zero-export setting still leaves installed inverter capacity and fault contribution for the network operator to assess.
A customer limitation scheme measures flow at the connection point and curtails output to meet the export limit agreed with the network operator. This may make a constrained site viable, but lost weekend or shutdown generation must be included in the business case. It cannot turn a large installed generator into a small one for fault-level, thermal or protection assessment. Ask the DNO to confirm the accepted capacity and whether reinforcement, flexible connection terms or a smaller design is needed.
NIE Networks administers G98/NI and G99/NI rather than the GB DNO process. Its fast-track rules changed on 1 May 2026: qualifying systems may have installed capacity up to 60 A per phase, subject to individual inverters no larger than 32 A and export no higher than 16 A per phase. Fast track still requires an application and approval before installation. Confirm the current scheme, permitted export and commissioning requirements with NIE Networks for your site.
Technical Compliance
Facilities managers and engineering team queries
No. G100 addresses export control, not connection approval. The network operator still checks installed inverter capacity, protection and fault contribution and must accept the proposed arrangement.
They can. A separate AC-coupled battery inverter may add to the capacity considered, while a battery sharing a hybrid inverter can be treated differently. Ask the engineer to show both arrangements on the single-line diagram.
It depends on the application route, whether the submission is complete, network constraints and any required works or witness tests. Ask the network operator for the applicable offer and commissioning programme; do not treat a quotation target as an installation date.
No. NIE Networks has separate G99/NI criteria. Even a qualifying fast-track proposal requires approval before installation; check the current rules with NIE Networks.
Share the supply details, proposed inverter capacity and any battery plans. A network operator must confirm the actual connection route and conditions.